January Work On The Woodville To Swadlincote Regeneration Route: How It Will Affect You

By Graham Hill

4th Jan 2021 | Local News

This month's planned work on the Woodville to Swadlincote regeneration route has been outlined by Derbyshire County Council.

Phase one will involve the new link road at the former open cast site in Woodville.

The council says: "Earthworks for the new road will continue during early January, with an aim to finish this part of the groundwork by the end of the month.

"Our work in this area was slower than expected during December because of bad weather and because we found unsuitable material, tyres and other controlled waste which had to be removed.

Work to begin on regeneration route

"Once the earthwork excavation is completed, we will move onto building up the four layers which make a modern highway construction.

"From mid-January we will begin work on installing new drainage connections at the Occupation Lane roundabout, and continue to build up levels in the new road across the former open cast area.

"This work at the roundabout will need temporary three way traffic lights.

"We are installing an 'on-demand' system, where the lights will react when traffic approaches them."

Phase two centres on a new roundabout on the A514 at Woodhouse Street in Swad.

The council adds: "The Woodhouse Business Centre work will be completed following its partial demolition to make way for for the roundabout.

Local enterprise partnership to help fund route

"At the A514 Derby Road, Swadlincote, Cadent Gas will begin diverting some of their services during the first week of January.

"This will need three way traffic lights at the A514 junction with Woodhouse Street, which will be in place for two weeks.

"Stone will be laid to form the foundation of the new roundabout."

Phase three will then be to join up phases one and two.

The council says: "At Kiln Way, Swadlincote, Cadent Gas will begin moving their gas supply in this area from 18th January.

"This will need three way temporary traffic lights at the junction of Kiln Way with Woodhouse Street for four weeks."

The overview of the programme says that the work should be completed by August.

* Complete Derby Road roundabout – expected May 2021

  • Complete Occupation Lane section to Kiln Way – expected May 2021
  • Work starts to modify and improve Kiln Way – expected May 2021
  • Complete Kiln Way section – expected August 2021

     

New swadlincote Jobs Section Launched!!
Vacancies updated hourly!!
Click here: swadlincote jobs

Share:

Related Articles

Michael Crawshaw with his latest work 'The Gerasimov Doctrine' (Image by Nub News)
Local News

'I thought the premise was a bit silly': Michael Crawshaw on writing, Russia and outsiders in his new book, The Gerasimov Doctrine

Hardwicke Circus will kick off their pub tour in Sheffield on September 26. (Credit: Hardwicke Circus and Pixabay)
Local News

Hardwicke Circus to bring critically-acclaimed rock 'n' roll sound to pubs all over the UK

Sign-Up for our FREE Newsletter

We want to provide swadlincote with more and more clickbait-free local news.
To do that, we need a loyal newsletter following.
Help us survive and sign up to our FREE weekly newsletter.

Already subscribed? Thank you. Just press X or click here.
We won't pass your details on to anyone else.
By clicking the Subscribe button you agree to our Privacy Policy.